$0.00
ISC2 CAP Exam Dumps

ISC2 CAP Exam Dumps

CAP â?? Certified Authorization Professional

395 Questions & Answers with Explanation
Update Date : March 06, 2024
PDF + Test Engine
$65 $95
Test Engine
$55 $85
PDF Only
$45 $75

Money back Guarantee

We just do not compromise with the bright future of our respected customers. PassExam4Sure takes the future of clients quite seriously and we ensure that our CAP exam dumps get you through the line. If you think that our exam question and answers did not help you much with the exam paper and you failed it somehow, we will happily return all of your invested money with a full 100% refund.

100% Real Questions

We verify and assure the authenticity of ISC2 CAP exam dumps PDFs with 100% real and exam-oriented questions. Our exam questions and answers comprise 100% real exam questions from the latest and most recent exams in which you’re going to appear. So, our majestic library of exam dumps for ISC2 CAP is surely going to push on forward on the path of success.

Security & Privacy

Free for download ISC2 CAP demo papers are available for our customers to verify the authenticity of our legit helpful exam paper samples, and to authenticate what you will be getting from PassExam4Sure. We have tons of visitors daily who simply opt and try this process before making their purchase for ISC2 CAP exam dumps.



Last Week CAP Exam Results

254

Customers Passed ISC2 CAP Exam

97%

Average Score In Real CAP Exam

98%

Questions came from our CAP dumps.



Authentic CAP Exam Dumps


Prepare for ISC2 CAP Exam like a Pro

PassExam4Sure is famous for its top-notch services for providing the most helpful, accurate, and up-to-date material for ISC2 CAP exam in form of PDFs. Our CAP dumps for this particular exam is timely tested for any reviews in the content and if it needs any format changes or addition of new questions as per new exams conducted in recent times. Our highly-qualified professionals assure the guarantee that you will be passing out your exam with at least 85% marks overall. PassExam4Sure ISC2 CAP ProvenDumps is the best possible way to prepare and pass your certification exam.

Easy Access and Friendly UI

PassExam4Sure is your best buddy in providing you with the latest and most accurate material without any hidden charges or pointless scrolling. We value your time and we strive hard to provide you with the best possible formatting of the PDFs with accurate, to the point, and vital information about ISC2 CAP. PassExam4Sure is your 24/7 guide partner and our exam material is curated in a way that it will be easily readable on all smartphone devices, tabs, and laptop PCs.

PassExam4Sure - The Undisputed King for Preparing CAP Exam

We have a sheer focus on providing you with the best course material for ISC2 CAP. So that you may prepare your exam like a pro, and get certified within no time. Our practice exam material will give you the necessary confidence you need to sit, relax, and do the exam in a real exam environment. If you truly crave success then simply sign up for PassExam4Sure ISC2 CAP exam material. There are millions of people all over the globe who have completed their certification using PassExam4Sure exam dumps for ISC2 CAP.

100% Authentic ISC2 CAP – Study Guide (Update 2024)

Our ISC2 CAP exam questions and answers are reviewed by us on weekly basis. Our team of highly qualified ISC2 professionals, who once also cleared the exams using our certification content does all the analysis of our recent exam dumps. The team makes sure that you will be getting the latest and the greatest exam content to practice, and polish your skills the right way. All you got to do now is to practice, practice a lot by taking our demo questions exam, and making sure that you prepare well for the final examination. ISC2 CAP test is going to test you, play with your mind and psychology, and so be prepared for what’s coming. PassExam4Sure is here to help you and guide you in all steps you will be going through in your preparation for glory. Our free downloadable demo content can be checked out if you feel like testing us before investing your hard-earned money. PassExam4Sure guaranteed your success in the ISC2 CAP exam because we have the newest and most authentic exam material that cannot be found anywhere else on the internet.


ISC2 CAP Sample Questions

Question # 1

Which of the following statements correctly describes DIACAP residual risk?

A. It is the remaining risk to the information system after risk palliation has occurred.
B. It is a process of security authorization.
C. It is the technical implementation of the security design.
D. It is used to validate the information system.



Question # 2

Which of the following is a standard that sets basic requirements for assessing the effectiveness of computer security controls built into a computer system?

A. TCSEC 
B. FIPS
 C. SSAA 
D. FITSAF



Question # 3

A security policy is an overall generalstatement produced by senior management that dictates what role security plays within the organization. What are the different types of policies? Each correct answer represents a complete solution. Choose all that apply.  

A. Systematic
B. Regulatory
C. Advisory
D. Informative



Question # 4

Which of the following processes is a structured approach to transitioning individuals, teams, and organizations from a current state to a desired future state?

A. Configuration management
B. Procurement management
C. Change management
D. Risk management



Question # 5

Which of the following is used to indicatethat the software has met a defined quality level and is ready for mass distribution either by electronic means or by physical media?

A. DAA
 B. RTM 
C. ATM 
D. CRO 



Question # 6

Which of the following statements aboutDiscretionary Access Control List (DACL)is true?  

A. It is a rule list containing access control entries.  
B. It specifies whether an audit activity should be performed when an object attempts to access a resource. 
C. It is a list containing user accounts, groups, and computers that are allowed (or denied) access to the object.
D. It is a unique number that identifies a user, group, and computer account  



Question # 7

During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?

A. Symptoms
B. Cost of the project
C. Warning signs
D. Risk rating



Question # 8

During which of the following processes,probability and impact matrixis prepared? 

A. Plan Risk Responses
B. Perform Quantitative Risk Analysis
C. Perform Qualitative Risk Analysis
D. Monitoring and Control Risks



Question # 9

Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for theproject have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?

A. Project contractual relationship with the vendor
B. Project communications plan
C. Project management plan
D. Project scope statement



Question # 10

Which of the following is NOT an objective of the security program? 

A. Security organization  
B. Security plan  
C. Security education  
D. Information classification  



Question # 11

In 2003, NIST developed a new Certification & Accreditation (C&A) guideline known as FIPS 199. What levels of potential impact are defined by FIPS 199? Each correct answer represents a complete solution. Choose all that apply.

A. Low 
B. Moderate 
C. High 
D. Medium 



Question # 12

An authentication method uses smart cards as well as usernames and passwordsfor authentication. Which of the following authentication methods is being referred to?

A. Anonymous 
B. Multi-factor 
C. Biometrics
 D. Mutual 



Question # 13

You work as a project manager for BlueWell Inc. There has been a delay in your project work that is adversely affecting the project schedule. You decided, with your stakeholders' approval, to fast track the project work to get the project done faster. When you fast track the project which of the following are likely to increase?

A. Risks
B. Human resource needs
C. Quality control concerns
D. Costs



Question # 14

Which of the following RMF phases is known as risk analysis? 

A. Phase 0
B. Phase 1
C. Phase 2
D. Phase 3



Question # 15

Which one of the following is the only output for the qualitative risk analysis process? 

A. Enterprise environmental factors  
B. Project management plan  
C. Risk register updates  



Question # 16

The Information System Security Officer (ISSO) and Information System Security Engineer (ISSE) play the role of a supporter and advisor, respectively. Which of the following statements are true about ISSO and ISSE? Each correct answer represents a complete solution. Choose all that apply.

A. An ISSE manages the security of the information system that is slated for Certification & Accreditation (C&A). 
B. An ISSO takes part in the development activities that are required to implement system ch anges.
C. An ISSE provides advice on the continuous monitoring of the information system.  
D. An ISSE provides advice on the impacts of system changes.  
E. An ISSO manages the security of the information system that is slated for Certification & Accreditation (C&A). 



Question # 17

Harry is a project manager of a software development project. In the early stages of planning, he and the stakeholders operated with the belief that the software they were developing would work with their organization's current computer operating system. Now that the project team has started developing the software it has become apparent that the software will not work with nearly half of the organization's computer operating systems. The incorrect belief Harry had in the software compatibility is an example of what in project management?

A. Assumption
B. Issue
C. Risk
D. Constraint



Question # 18

Which of the following DITSCAP phases validates that the preceding work has produced an IS that operates in a specified computing environment?

A. Phase 3
B. Phase 2
C. Phase 4
D. Phase 1



Question # 19

Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project." 

A. Perform Quantitative Risk Analysis
B. Monitor and Control Risks
C. Perform Qualitative Risk Analysis
D. Identify Risks



Question # 20

There are seven risk responses for any project. Which one of the following is a valid risk response for a negative risk event?

A. Enhance  
B. Exploit  
C. Acceptance  
D. Share  



Question # 21

In which type of access control do user ID and password system come under? 

A. Administrative
B. Technical
C. Physical
D. Power



Question # 22

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

A. No, the ZAS Corporation did not complete all of the work.
B. Yes, the ZAS Corporation did not choose to terminate the contract work.
C. It depends on what the outcome of a lawsuit will determine.
D. It depends on what the terminationclause of the contract stipulates



Question # 23

Shoulder surfing is a type of in-person attack in which the attacker gathers information about the premises of an organization. This attack is often performed by looking surreptitiously at the keyboard of an employee's computer while he is typing in his password at any access point such as a terminal/Web site. Which of the following isviolated in a shoulder surfing attack?

A. Authenticity
B. Integrity
C. Availability
D. Confidentiality



Question # 24

Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?

A. Work breakdown structure
B. Roles and responsibility matrix
C. Resource breakdown structure
D. RACI chart



Question # 25

Which of the following DoD directives is referred to as theDefense Automation Resources Management Manual?

A. DoD 5200.22-M
B. DoD 5200.1-R
C. DoD 8910.1
D. DoDD 8000.1
E. DoD 7950.1-M



Question # 26

Tom is the project manager for his organization. In his project he has recently finished the risk response planning. He tells his manager that he will now need to update the cost and schedule baselines. Why would the risk response planning cause Tom the need to update the cost and schedule baselines?

A. New or omitted work as part of a risk response can cause changes to the cost and/or schedule baseline. 
B. Risk responses protect the time and investment of the project.
C. Risk responses may take time and money to implement.
D. Baselines should not be updated, but refined through versions.



Question # 27

Which of the following guidance documents is useful in determining the impact level of a particular threat on agency systems?

A. NIST SP 800-41
B. NIST SP 800-37
C. FIPS 199
D. NIST SP 800-14



Question # 28

Which of the following documents is used to provide a standard approach to the assessment of NIST SP 800-53 security controls?

A. NIST SP 800-53A
B. NIST SP 800-66
C. NIST SP 800-41
D. NIST SP 800-37