We just do not compromise with the bright future of our respected customers. PassExam4Sure takes the future of clients quite seriously and we ensure that our Prince2-Foundation exam dumps get you through the line. If you think that our exam question and answers did not help you much with the exam paper and you failed it somehow, we will happily return all of your invested money with a full 100% refund.
We verify and assure the authenticity of PRINCE2 Prince2-Foundation exam dumps PDFs with 100% real and exam-oriented questions. Our exam questions and answers comprise 100% real exam questions from the latest and most recent exams in which you’re going to appear. So, our majestic library of exam dumps for PRINCE2 Prince2-Foundation is surely going to push on forward on the path of success.
Free for download PRINCE2 Prince2-Foundation demo papers are available for our customers to verify the authenticity of our legit helpful exam paper samples, and to authenticate what you will be getting from PassExam4Sure. We have tons of visitors daily who simply opt and try this process before making their purchase for PRINCE2 Prince2-Foundation exam dumps.
Customers Passed PRINCE2 Prince2-Foundation Exam
Average Score In Real Prince2-Foundation Exam
Questions came from our Prince2-Foundation dumps.
PassExam4Sure is famous for its top-notch services for providing the most helpful, accurate, and up-to-date material for PRINCE2 Prince2-Foundation exam in form of PDFs. Our Prince2-Foundation dumps for this particular exam is timely tested for any reviews in the content and if it needs any format changes or addition of new questions as per new exams conducted in recent times. Our highly-qualified professionals assure the guarantee that you will be passing out your exam with at least 85% marks overall. PassExam4Sure PRINCE2 Prince2-Foundation ProvenDumps is the best possible way to prepare and pass your certification exam.
PassExam4Sure is your best buddy in providing you with the latest and most accurate material without any hidden charges or pointless scrolling. We value your time and we strive hard to provide you with the best possible formatting of the PDFs with accurate, to the point, and vital information about PRINCE2 Prince2-Foundation. PassExam4Sure is your 24/7 guide partner and our exam material is curated in a way that it will be easily readable on all smartphone devices, tabs, and laptop PCs.
We have a sheer focus on providing you with the best course material for PRINCE2 Prince2-Foundation. So that you may prepare your exam like a pro, and get certified within no time. Our practice exam material will give you the necessary confidence you need to sit, relax, and do the exam in a real exam environment. If you truly crave success then simply sign up for PassExam4Sure PRINCE2 Prince2-Foundation exam material. There are millions of people all over the globe who have completed their certification using PassExam4Sure exam dumps for PRINCE2 Prince2-Foundation.
Our PRINCE2 Prince2-Foundation exam questions and answers are reviewed by us on weekly basis. Our team of highly qualified PRINCE2 professionals, who once also cleared the exams using our certification content does all the analysis of our recent exam dumps. The team makes sure that you will be getting the latest and the greatest exam content to practice, and polish your skills the right way. All you got to do now is to practice, practice a lot by taking our demo questions exam, and making sure that you prepare well for the final examination. PRINCE2 Prince2-Foundation test is going to test you, play with your mind and psychology, and so be prepared for what’s coming. PassExam4Sure is here to help you and guide you in all steps you will be going through in your preparation for glory. Our free downloadable demo content can be checked out if you feel like testing us before investing your hard-earned money. PassExam4Sure guaranteed your success in the PRINCE2 Prince2-Foundation exam because we have the newest and most authentic exam material that cannot be found anywhere else on the internet.
Which statement about the quality review technique is FALSE?
A. It enables a check to be made on a product's fitness for purpose
B. It defines the quality responsibilities of the project team
C. It supports the management of future changes by providing a baseline for a product
D. It is used to gain wider acceptance of a product by involving key interested parties
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
A. quality
B. supplier
C. risk
D. product
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities
A. change budget
B. project budget
C. project's cost tolerance
D. project's risk tolerance
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
A. Project Brief
B. Project Initiation Documentation
C. Project mandate
D. Benefits Review Plan
Which is part of quality control?
A. Undertake quality reviews
B. Write Product Descriptions
C. Provide assurance that the project is being conducted properly
D. Document the customer's quality expectations
Identify the missing word in the following sentence. The guiding obligations and good practices that determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
A. Principles
B. Themes
C. Processes
D. Techniques
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity
A. Avoid
B. Reduce
C. Share
D. Transfer
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A. Configuration Item Record
B. Quality Register
C. Highlight Report
D. Checkpoint Report
Which should be funded by a change budget?
A. Increase in agreed scope
B. Increase in agreed scope
C. Increase in agreed scope
D. Handover activities
Which should be provided by corporate or program management before the Starting up a Project process commences?
A. A Project Brief
B. Sufficient information to identify the prospective Executive
C. The Project Initiation Documentation
D. Authority to initiate a project
Whose approval is needed to replace a Stage Plan with an Exception Plan?
A. Corporate or programme management
B. Project Board
C. Project Manager
D. Team Manager
What is an off-specification?
A. A new requirement
B. A quality tolerance
C. A type of issue
D. A major risk
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
A. Benefits
B. Quality
C. Risk
D. Scope
Which is NOT one of the PRINCE2 integrated elements?
A. Tailoring PRINCE2 to the project environment
B. The processes
C. The products
D. The themes
Which is the Issue Register NOT used for?
A. Capture external events that are impacting a stage
B. Record information about a deviation in stage tolerance
C. Capture any threats or opportunities that might have an impact on a stage
D. Record any problems identified when authorizing a Work Package
Which is a purpose of the Risk Register?
A. Describe the risk management techniques and standards to be applied to the project
B. Act as a central record of information relating to the identified risks for the project
C. Act as a repository for informal issues
D. List the responsibilities for achieving an effective risk management procedure
Which is NOT considered when defining risk tolerance?
A. A Project Board's attitude towards risk-taking
B. The allocated risk budget
C. An organization's risk appetite
D. The amount of risk a Project Board considers acceptable
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
A. Closing a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project
Which statement about the Directing a Project process is true?
A. Provides a mechanism for the Project Board to assure that there is a continued business justification
B. Covers the day-to-day activities of the Project Manager
C. Ensures there are regular progress meetings
D. Begins on completion of the Initiating a Project process
How many management stages should a PRINCE2 project consist of?
A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage
Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts